Southport Market Quarter Guest Blog by Maisie O’Garra, Balfour Beatty
We are committed to keeping the public informed about our project schedule and progress. We are pleased to confirm that we are adhering to our planned programme of works and do not anticipate any delays and are scheduled to finish by November as planned.

Eastbank Street upcoming works
Works to the north side of Eastbank street (Chapel Street side) will include the removal of existing kerbs and footpath paving, the installation of 4 new tree pit crates and soil, 1 is already complete.
We will be repositioning 2 existing street lighting columns and installing new kerb lines and paving. Pedestrian access is maintained along the buildings while these improvements are underway.
Paving works through Sharrock Street and Chapel Street will be coordinated with local stakeholders to ensure minimal disruption.
All works on this footpath are expected to be finished by the end of June.

Phase 1 works are now complete, with pedestrian access maintained along the buildings work is scheduled to recommence in this area (Phase 4) at the end of June, once the northern footpath is complete.
The next phase will begin with the excavation for drainage pipework and the installation of permeable paving.

King Street Updates
We are pleased to provide an update on the ongoing works on King Street. Current progress on the Eastern Footpath (Market side): The footpath is 80% complete and pedestrian routes are currently available on both sides of the street.
Ongoing works for the carriageway construction include the Installation of new kerb lines, final trim of the carriageway foundation and Installation of surfacing to the carriageway.
Additional activities will include excavation and installation of a new permeable paving and drainage system, placement of soil in rain gardens and removal of existing lighting and installation of new columns.
Once carriageway works are complete, paving works will commence on the western footpath. Please note that walkways are subject to change as work progresses; however, access will be provided at all times. If assistance is required, please ask a member of the site team.

Market Street upcoming works
Both sides of footpaths are now 90% complete on Market Street with works ongoing to the carriageway section.
We are pleased to announce that by the end of June, the majority of fencing to Market Street will be taken away leaving the new outdoor space for the shops and Southport Market.
We hope this will encourage people to use the outdoor space throughout the summer months although we will have to return to the area to carry out some remaining works and to install the planting during the planting season.

King Street – Market Street junction upcoming works
We are providing an update on the upcoming works at the King Street – Market Street Junction.
Works are due to commence here in June.
These Works will be completed in a phased approach to maintain traffic flow.
The activities in this area of works will include the removal of existing surfacing on the north-east corner and the excavation for new drainage and carriageway construction.
Please note that walkways are subject to change as work progresses; however, access will be provided at all times. If assistance is required, please ask a member of the site team.

Update on Project Schedule and Phasing of Works
Our approach utilises phasing, which involves working on different areas of the project simultaneously. This method helps us complete the project more efficiently.
Phasing the works allows us to reduce the time we spend working in any particular area.
If we were to prioritise finishing some areas before starting others, the overall scheme would take much longer to complete, resulting in extended periods of disruption.
By managing multiple areas concurrently, we ensure that our presence and impact in any given location are kept to a minimum.
In line with our plans, we are excited to announce that Market Street will be fully pedestrianised.
The Traffic Regulation Order (TRO) necessary for the pedestrianisation of Market Street is progressing well. This initiative will provide a more pleasant and safer environment for pedestrians and contribute positively to the local community.
We understand that businesses on Market Street may have questions regarding loading and logistics. To address these concerns, we will be writing separately to businesses in the area to discuss alternative loading arrangements.
Our team is dedicated to finding solutions that mitigate any inconvenience and support local businesses during this transition. Your understanding and cooperation are greatly appreciated as we work towards enhancing the area for everyone.
We remain committed to keeping you updated on further developments and appreciate your patience during this period of improvement.

The Les Transformations vision
The vision for the Les Transformations project is to create accessible, well connected and high-quality public spaces, improving footfall between all areas of Southport town centre.
This will support businesses in attracting and retaining customers, improve the health and wellbeing of communities, encourage people to stay longer or return more frequently and thereby reinforce the vision for the town.
Contact Us
If you have any questions about the works please do not hesitate to contact us: LTDS.Queries@balfourbeatty.com
Do you have a story for Stand Up For Southport? Do you need advertising, PR or media support? Please message Andrew Brown via Facebook here or email me at: mediaandrewbrown@gmail.com